Project Timeline

 

Nov. 2014 - May 2015  Project Development 
     
June 5, 2015  Filed Application with Federal Energy Regulatory Commission (FERC) 
     
January 27, 2016  FERC Issued the Environmental Assessment 
     
March 24, 2016   FERC Granted Approval  
     
June 3, 2016 FERC Provided Notice to Proceed with Construction
         
July 13, 2016  Construction Commenced at Crosby Compressor Station 
     
July - September 2016 Construction Commenced on Existing Compressor Station Reversals
   
March 2, 2017 Placed In-Service the Crosby Compressor Station and Existing Station Reversals at Bastrop CS, Covington CS, Slaughters CS, Hardinsburg CS, Jeffersontown CS, and Leesville CS
   
April 7, 2017 Filed Request for Extension of Time to Construct and Make Certain Project Facilities Available for Service (Link to Request)
   
October 19, 2017 FERC issued Approval of Extension of Time (Link to Approval)    

 

 

Items shown in red font reflect the latest updates.